How to Price Land Clearing Jobs (Per-Acre Rates + Free Bid Worksheet)

Most land clearing bids get made in a driveway, from the truck, with a number that "feels right." Sometimes it is. Often it quietly costs you money on the jobs you win and loses you the jobs you should have won. Here is a simple method you can repeat on every bid: know what a crew-day costs, know how much you clear in a day, and price from there. To follow along on paper, open the free Land Clearing Bid Worksheet in another tab.

Quick answer: price per acre = (crew-day cost ÷ acres you clear per day at that density) × (1 + your margin). With a $1,600 crew-day, one acre a day of medium brush and a 30% margin, that is about $2,080 per acre. Then add mobilization, stumps, haul-off and large trees as separate line items, and set a minimum charge.

Step 1: Work out what one crew-day really costs you

Every price starts here. Add up what it costs to have your crew and machines out for one full working day, whether or not the day goes well:

  • Labor: wages for everyone on the crew, plus payroll taxes and workers' comp.
  • Equipment: the daily share of loan or lease payments for the track loader, mulcher head, excavator, truck and trailer. Divide the monthly payment by the days you actually work in a month, not by 30.
  • Fuel: a forestry mulcher burns through diesel. Track a few real days and use the average.
  • Wear and maintenance: teeth, hydraulic hoses, undercarriage, filters and oil. Mulcher teeth alone add up fast in rocky or sandy ground.
  • Insurance: general liability, inland marine on the equipment and commercial auto, divided by working days.
  • Overhead: phone, software, marketing, yard rent and your own time on estimates.

Write the total down. That's your break-even day. If your crew-day costs $1,600 and you charge $1,600 for a day of work, you've bought yourself a very tiring day at zero profit.

Step 2: Know how many acres you clear per day at each density

Your production rate turns a day cost into a per-acre price, and it changes a lot with what's on the ground. Keep a separate number for each density:

  • Light: pasture, palmetto, briars, saplings under 2 inches.
  • Medium: thick brush, small trees, scattered 4 to 6 inch hardwoods.
  • Heavy: wooded lot, mature trees, lots of stumps to grub.
A 100 hp mulcher on flat sandy ground and a smaller machine on a steep, rocky slope are not the same business, so track your own. Write down start time, end time and acres on your next ten jobs and you'll have real numbers within a month.

Then adjust for what slows you down: slopes, wet ground, rock, fences or structures to work around, tight access, and selective clears where the customer wants certain trees saved.

Step 3: Turn cost and production into a price

Price per acre = (crew-day cost ÷ acres per day) × (1 + margin)

Example: your crew-day costs $1,600 and you clear one acre of medium brush per day. Break-even is $1,600 per acre. Add a 30% margin and you land around $2,080 per acre. On a 3-acre medium lot that is about $6,240 before line items.

A margin around 30% is a common starting point. Push it higher for heavy timber, difficult access and jobs with a lot of unknowns. If you find yourself cutting it to win jobs, the real problem is usually lead flow, not price. More on that in how to get land clearing leads.

Step 4: Sanity-check against the market

Once you have your own number, compare it to what homeowners are seeing. 2026 homeowner cost guides from sites like Lawn Love and ContractorPlus put lightly forested land roughly in the $600 to $2,300 per acre range and heavily forested land roughly $3,300 to $6,000+. Hourly land clearing labor is commonly quoted around $120 to $300 per hour, depending on region and machine.

Use those ranges to spot problems, not to set your price. Far below them? Check whether you left something out of your day cost. Far above? Make sure your quote explains what the customer gets for it.

Step 5: Price the line items separately

Customers compare quotes more fairly, and you lose fewer arguments, when extras are spelled out:

  • Mobilization: a flat fee for loading, hauling and setup, more past a set mileage.
  • Stump grinding or grubbing: per stump or per acre. Grubbing heavy stumps can double the time on a lot.
  • Haul-off and disposal: per load or per acre, including dump fees. On a mulching job, say plainly that the mulch stays on site.
  • Large tree removal: anything bigger than your mulcher handles, priced per tree.
  • Permits and surveys: who pulls the permit and who marks property lines and protected trees.
  • Finish work: rough grading, seeding or a driveway cut if you offer it.

Step 6: Set a minimum charge

Small jobs eat the same mobilization time as big ones. Set a minimum of at least half a crew-day plus mobilization, and say so on the phone before you drive out. It filters out the quarter-acre-for-$300 calls and keeps your schedule open for real work.

Step 7: Write the quote so it closes

A price in a text message loses to a slightly higher price on a clear one-page quote. Include:

  • The property address and the area being cleared, with a rough sketch or marked aerial photo.
  • The method (forestry mulching, clear and haul, selective clearing) and what the site will look like when you leave.
  • Every line item from Step 5, marked included or not included.
  • Your start window, how many days it should take, and what happens if weather pushes it.
  • Payment terms, deposit and your insurance information.
  • How long the price is good for.

Then follow up. A short text around day three and again around day ten wins a surprising number of jobs that would have gone quiet.

Common land clearing pricing mistakes

  • Pricing from a competitor's number. You don't know their costs, their debt, or whether they're making money.
  • Forgetting the drive. Two hours each way is a quarter of the crew-day before the mulcher starts.
  • Not updating fuel and teeth costs. Recheck your crew-day cost every quarter.
  • Pricing before seeing the lot. Give a range on the phone and a firm number after a site visit or good photos and an aerial.

Frequently asked questions

How much should I charge per acre for land clearing?

Work out your crew-day cost, divide by your realistic acres per day at that density, and add your margin. Use published market ranges only as a sanity check.

Should I charge by the hour or by the acre?

Per-acre or per-job pricing is easier for customers to accept and rewards you for working efficiently. Keep an hourly rate for small, unclear jobs and add-ons.

What is a fair minimum charge for land clearing?

At least half a crew-day cost plus mobilization.

Do I include stumps and haul-off in the per-acre price?

List them separately so the customer sees what they're paying for and compares quotes fairly.