Excavation estimates go wrong in two places: the dirt you can't see, and the costs you forgot to count. A driveway that looked like a two-day job turns into four when you hit clay and have to import stone, and the trucking eats the margin. This guide gives you a repeatable way to price excavation jobs, plus a free estimate template you can print.
Quick answer: price excavation from your real hourly machine-and-crew cost, a quantity takeoff (cubic yards to dig, haul or import), and your honest production rate for that soil. Add trucking, materials, disposal, permits and mobilization as separate lines, then apply your markup for overhead and profit and a contingency for unknown ground.
Step 1: Build your hourly rate for each machine and crew
Before you can price a job, you need to know what an hour of each setup really costs you. For each machine (mini excavator, full-size excavator, skid steer or CTL, dozer, dump truck), add up:
- Ownership: loan or lease payment, depreciation, insurance and storage, divided by the hours it actually works per year.
- Operating: fuel, oil, filters, tracks or tires, teeth and repairs per hour.
- Operator: wage plus payroll taxes, workers' comp and benefits per hour.
Add your general overhead per working hour (office, phone, software, marketing, yard, estimating time). The total is your break-even hourly rate for that setup. Write each one down; you'll use them on every bid.
Step 2: Pick the right pricing method for the job
- Hourly (time and materials): best for small, unclear jobs and add-ons where the customer accepts the risk.
- Per cubic yard: best for mass digging, pads, ponds and import or export of fill, where the quantity drives the time.
- Per linear foot: best for trenching, utility lines, French drains and footers.
- Lump sum (fixed bid): best for well-defined residential jobs (driveway, pad, septic). Customers prefer it, but you carry the risk, so the contingency matters.
Step 3: Do a quantity takeoff
Cubic yards = length (ft) × width (ft) × depth (ft) ÷ 27. A 100 × 12 ft driveway cut 1 ft deep is about 44 cubic yards of excavation, plus whatever stone goes back in.
Account for swell: excavated soil takes up more space loose than it did in the ground, so you'll haul more truckloads than the bank volume suggests. Use the swell factor for your soil type (clay swells more than sand), and count truckloads from the loose volume.
Step 4: Estimate production honestly
Production is how many yards or feet you move per hour, and it depends on the machine, the operator, the soil, the cycle time, and how far the trucks travel. Track a few real jobs: start time, end time, yards moved. Your own numbers beat any chart. Then adjust for wet ground, rock, tight access, working around structures and utilities, and haul distance. Hours = quantity ÷ production rate.
Step 5: List the costs that kill margins
- Mobilization: loading, hauling and setup for every machine, each way.
- Trucking: truck hours or loads for export and import, including wait time.
- Materials: stone, fill, pipe, fabric, culverts, priced per ton or yard, delivered.
- Disposal and dump fees: clean fill vs. debris rates differ.
- Permits, utility locates and inspections: who pulls, who pays, and the time on site waiting.
- Erosion control: silt fence, inlet protection, seeding and straw.
- Compaction and testing where specs require it.
- Restoration: topsoil, grading, seed, fixing the yard you drove across.
Step 6: Add markup and contingency
Total direct cost = machine and crew hours × rates + trucking + materials + disposal + permits + mobilization. Apply your markup for profit on top of break-even, and a contingency for unknown subsurface conditions (more for jobs with no soil information, less for jobs you've done next door). If you're cutting markup to win work, the problem is usually lead flow; see how to get excavation leads.
Free excavation estimate template
Copy or print this (Ctrl/Cmd+P). No email required.
Job: customer, address, scope ______________________________
Soil and site notes: soil type, water, rock, access, utilities ______________________________
Quantities: excavation ____ yd³ (bank) → ____ yd³ (loose) • import ____ yd³/tons • trench ____ LF
Machine 1: ____ hrs × $____/hr = $______
Machine 2: ____ hrs × $____/hr = $______
Trucking: ____ loads/hrs × $____ = $______
Labor (non-operator): ____ hrs × $____ = $______
Materials: ______________ = $______
Disposal / dump fees: $______
Permits, locates, inspections: $______
Erosion control and restoration: $______
Mobilization: $______
Direct cost subtotal: $______
Contingency (___%): $______
Markup (___%): $______
TOTAL BID: $______
☐ Exclusions listed (rock, unsuitable soil, utilities not marked) ☐ Start window and duration ☐ Payment terms and deposit ☐ Price valid until ____ ☐ Follow-up set for day 3 and day 10
Step 7: Write a quote that protects you
Spell out the scope, quantities, what's included and excluded (especially rock, unsuitable soils, unmarked private utilities and groundwater), how changes are priced (your hourly rates), the start window, payment terms and how long the price is good for. Clear exclusions are the difference between a change order and an argument.
Frequently asked questions
How do you calculate an excavation estimate?
Quantity takeoff ÷ production rate = hours; hours × your hourly machine and crew rates, plus trucking, materials, disposal, permits and mobilization; then add contingency and markup.
Should I bid excavation hourly or lump sum?
Lump sum for well-defined jobs where you trust the quantities; hourly or unit pricing for unclear scopes and add-ons.
How do I account for soil swell when pricing hauling?
Convert bank cubic yards to loose cubic yards using the swell factor for your soil, then count truckloads from the loose volume.
More free tools
- Land Clearing Bid Worksheet
- Excavation business plan template
- How to get excavation leads
- All free resources for dirt contractors
Bids priced, schedule still thin?
We build lead systems for excavation contractors with a 15 qualified lead guarantee. One contractor per county. See how we handle excavation marketing and Google Ads management.
See if your county is open